At the Lower Thames Crossing’s first media site tour, we saw the world’s largest electric articulated haulers at work and asked what they mean for the wider industry.

There is something surreal about watching a 40-tonne-class articulated hauler at work without the sound of a diesel engine. At the Lower Thames Crossing’s Station Road compound in East Tilbury, Essex, tyres moving through mud are now louder than the machinery itself.

Taking centre stage at the tour on 24 November 2026 were four Volvo A40 Electric articulated dump trucks (ADTs), which National Highways describes as the world’s largest electric articulated haulers in production and the first battery-powered machines in their size class to start work on site anywhere in the world. Supplied by SMT GB, Volvo CE’s UK dealer, they are working for BMJV, the Bouygues Travaux Publics and Murphy joint venture, moving aggregates for the tunnelling platforms and approaches.

The scheme, estimated at around £10.6 billion, will connect Kent and Essex through 14.3 miles (23km) of new road, including twin 2.6-mile (4.2km) tunnels beneath the Thames that will be the UK’s longest road tunnels. It aims to relieve the Dartford Crossing, which was designed for around 135,000 vehicles a day but now handles an average of 150,000. The road is expected to open in the early to mid-2030s.

Each A40 Electric has a 39-tonne payload, a 24m³ heaped body and a 540kWh battery. It is designed to match its diesel equivalent on performance, payload and tractive force, and keeps familiar controls, but produces no exhaust emissions at the point of use.

“Going electric no longer means compromising on size, power or productivity,” said Shaun Pidcock, programme director for the Lower Thames Crossing.

The haulers are charged overnight and topped up during breaks. Phil Battle, managing director of SMT GB, said they achieve five to six hours of operation, with opportunity charging covering a full shift. But he cautioned against direct comparison, as 30–40% of recorded diesel engine hours can be spent idling.

“The key point with electric equipment is there’s no idle time,” Battle said.

Cost has long been a barrier to electric machinery, but Battle believes that is changing: “We’re seeing not just parity but actually the electric coming out cheaper when you run it over a project cycle.”

National Highways forecasts a lower whole-life cost than for diesel or HVO equivalents, despite the higher purchase price, though this has yet to be independently demonstrated.

National Highways intends the Lower Thames Crossing to be the first major UK infrastructure project to achieve carbon neutrality in construction. Conventional diesel has not been permitted on its sites since 2025, another first for a major British infrastructure project. The 63 million litres it would otherwise have needed will be replaced with a mixture of electric, hydrogen and HVO biofuel. Around 150 zero-emission machines are forecast by peak construction in 2028.

“The operator feedback has been stunning,” said Neesha Pandya, head of low carbon delivery at the Lower Thames Crossing. “Operators are feeding back that actually at the end of the shift they feel fresher, better.”

Operator Andrea Naculai said the quieter cab made it easier to pay attention to her surroundings.

The real test will come over thousands of working shifts rather than a single site visit. But asked to compare the electric hauler with its diesel predecessor, Naculai did not hesitate:

“Everything is better.”